Project Snapshot
Client: Market-leading medical imaging equipment provider
Equipment: MRI system
Site: University College London Hospital (UCLH)
Access: Lower basement via a ventilation shaft
Planning: Approximately five months
Execution: Five-day delivery programme
The Brief
A market leading provider of medical imaging equipment required a specialist transportation company to assist in offloading a new MRI System from third-party transport at University College London Hospital (UCLH). This requirement presented several challenging tasks for medical equipment movers as the system was needed within the lower basement of the central London site.
The Response
As standard, Flegg Projects representatives thoroughly assess sites for all possible outcomes before making suitable suggestions that consider factors such as accessibility, time and costs. For the MRI System, a Project Manager attended UCLH to meet with various stakeholders and outline the key issues preventing a straight-forward installation. It was identified the route to the basement was via a ventilation shaft. Initial detailed safety documents including a risk assessment, method statement, lifting plan and drawings were provided. Additional visits would also be made before delivery to ensure success and the implementation of all final arrangements.