Project Snapshot
Client: Blue-chip manufacturer
Project: Factory closure and global relocation
Assets Relocated: Hundreds of sensitive, high-value assets
Destinations: Brazil, Mexico, Poland, Hungary, Bulgaria, the Netherlands and Indonesia
Duration: Approximately 18 months
Our Role: Machinery removal, export packing, global transport and final site clearance
The Challenge
Flegg Projects have been involved with this client for over 20-years; successfully installing new machinery and internal equipment re-locations at the site in East Anglia.
The decision was made to close the site and move production to sites scattered across the globe. Flegg were tasked with the removal of hundreds of sensitive and high-value assets from the site to include export packing and transport to destination.
The Solution
Having worked at the site for many years, the Flegg team were already very familiar with the client’s expectations, the site layout and types of machinery and processes that were being carried out. The disruption of the works needed to be carefully balanced with the clients demands in terms of production – to ensure that their targets were maintained.